Call us today0800 160 1298
 
 

Latest News

  • A large scale contract dispute claim has commenced involving a Hull based energy plant and one of its main contractors. The plant – Energy Works Hull – terminated the contract for MW High Tech Projects as they claim that the contractor had not met the agreed project completion date. Energy Works Hull are seeking £133m in damages to cover the cost of rectifying defects, delay damages and added costs to complete works. In response, MW High Tech Projects is disputing the claim and has subsequently filed a counterclaim for just under £47m, based on provisions they say are in the original contract that provide for payment following a termination for convenience. The two parties are now heading for the High Court with claims and counterclaims stemming from failure to deliver the project, termination of the main contract and assignment of a key... Read More

  • Engineering and construction firm Bechtel now has a court date set to enable its appeal against the award of the HS2 £1bn Old Oak Common station construction partner contract. Read More

  • Whilst Covid-19 may have forced many parts of society to slow down and re-think our approach to all aspects of our lives, recent comments by a number of High Court judges would seem to indicate that this is certainly not happening in civil and commercial litigation. The 3 judges have expressed their disquiet over the ever increasing pervasiveness of hostile and antagonistic approaches to litigation where every point, good or bad, is taken. In the case of Navigator Equities Ltd & Ors v Deripaska from July this year, Mr Justice Andrew Baker said that, in the 30 years in which he had worked in commercial dispute resolution: There has been a significant general increase in hostility and aggressiveness in the conduct of disputes…the taking of any and every point, good or bad, and other failures to display proper independence from the litigating client... Read More